Authors:A Polish Perspective on BAT Conclusions.
The main piece of EU legislation regulating the environmental impact of large industrial installations is Directive 2010/75/EU of the European Parliament and of the Council of 24 November 2010 on industrial emissions. The so-called 'BAT Conclusions' (BAT = best available technology) are among the novelties that Directive 2010/75/EU introduced into the EU law. The concept is that BAT is a moving target, since technologies and social values are continually changing.
In formal terms, the BAT Conclusions mean a document containing the parts of a BAT reference document laying down the conclusions on best available techniques, their description, information to assess their applicability, the emission levels associated with the best available techniques, associated monitoring, associated consumption levels and, where appropriate, relevant site remediation measures*.
BATs for a given industrial sector are described in BAT Reference documents (BREFs).
In practical terms, the BAT Conclusions are a summary of the BREF reference documents, formally binding upon the authorities of the member states, prepared by the European Commission.
While the BREF reference documents are extensive (for example, the Polish version of the final draft of BREF of June 2016 for large combustion plants has 976 pages), BAT conclusions are significantly condensed (the Polish version of the BAT conclusions for large combustion plants has only 82 pages).
The current status of the work on updating BREF reference documents and adopting the BAT Conclusions by the European Commission for the individual types of installations covered by Directive 2010/75/EU can be tracked on the European Commission website or the website of the Polish Ministry of the Environment. The latter contains significant information for operators of the installations in Poland on the date by which these need to be adjusted to meet the requirements of the BAT Conclusions.
Much has been written and said mainly about the July BAT Conclusions for large combustion plants in Poland, for three main reasons. First, the significance of the conclusions for the Polish power industry that is predominantly based on coal. Second, the fact that the Polish government challenged the Commission’s decision before the Court of Justice of the European Union (CJEU). And finally, the Ministry of the Environment's provision of a manual on granting derogations from the obligation to adjust installations to BAT Conclusions requirements.
The fundamental obligation arising under the BAT Conclusions, that is adjustment of installations to the new requirements within four years from their publication by the European Commission, applies to existing installations (plants). According to the Polish Ministry of the Environment, in terms of the BAT Conclusions for fuel combustion plants, such an installation is one that, on the date of their publication (17 August 2017), held an integrated permit, even if not yet enforceable and final in the course of administrative proceedings. This view must be deemed quite lenient. Since the BAT conclusions include no transitional provisions, in contrast to the existing installations (plants), new installations (plants), that is those that on the date of publication of the BAT conclusions did not hold the above permit, are required to meet the requirements of the BAT conclusions immediately, i.e. on the date of obtaining the required environmental decisions and (integrated) permits.
The structure of the Commission’s decision establishing the BAT conclusions for the individual types of installations is similar to that of the BAT conclusions for large combustion plants. That is why the position of the Ministry of the Environment on the interpretation of the terms existing installation and new installation adopted for the purposes of the conclusions for large combustion plants will also apply as appropriate to the BAT conclusions adopted for other industries.
Directive 2010/75/EU provides for a Member State granting a derogation from the obligation to adjust the existing installations to the BAT requirements. The relevant provision of the Directive is quite general. That is why, for large combustion plants, the Ministry of the Environment provided a manual on how to grant the above derogations to remain in compliance with the Directive. The manual, although it formally addresses the BAT conclusions for large combustion plants, may have a much broader application, i.e. it can apply as appropriate to all the BAT conclusions adopted by the Commission.
According to the Environment Protection Law, the so-called cost derogation is granted in the course of proceedings to amend an integrated permit. In specific cases, the competent authority to issue the integrated permit may, in the integrated permit being amended, allow a derogation from emission limit values if its assessment shows that achievement of those limits would lead to disproportionately higher costs compared to the environmental benefits and providing that the emission standards, if applicable, are not exceeded.
In its assessment, the competent authority takes into account the geographical location, local environmental conditions, technical characteristics of the installation concerned, or other factors affecting the operation of the installation and the environment as a whole. To apply the derogation, public participation in the proceedings must be ensured.
The manual provided by the ministry provides sets out three types of derogations:
type A derogation – indefinite, providing that periodic reviews of the expediency of maintaining the derogation are carried out;
type B derogation – standard, fixed-term (e.g. decommissioning or upgrade not possible within four years);
type B1 derogation – fixed-term, granted due to the need to ensure security of electricity supply; applies to some of the centrally dispatched generating units and centrally coordinated generating units.
* Article 3(12) of the Directive, adopted by the European Commission in the form of decisions; Article 13.5 of the Directive, being the reference for setting the integrated permit conditions (Article 14(3) of the Directive)
Source: BPCC Contact magazine No. 32 (127) 2017, http://bpcc.org.pl/contact-magazine/issues/21/categories/99/articles/615
From 25 May 2018 the General Data Protection Regulation (GDPR) applies in Poland and other European Union countries. We would therefore like to give you several details on the subject of how DZP processes personal data.
The administrator of the personal data is Domański Zakrzewski Palinka Sp.k. (“DZP”; address: Rondo ONZ 1, 00-124 Warszawa). Data are processed for contact purposes and to impart information on changes to provisions and authority practices and on other issues, including events concerning day-to-day legal, economic and cultural issues, inter alia, by sending DZP newsletters. The above is carried out on the basis of legitimate interests, i.e. in accordance with art. 6(1)(f) of the GDPR. Data can also be processed where necessary for the conclusion or performance of a contract and for compliance with a legal obligation to which DZP is subject, i.e. pursuant to art. 6(1)(b) and (c) of the GDPR. Data can be transferred to entities with whose help DZP achieves the indicated aims, including entities maintaining IT infrastructure. Giving data is voluntary and in contractual relations is a requirement for concluding and performing a contract. It is possible to object to data processing, request access to, rectification and erasure of personal data or restriction of processing and data portability. Data are kept until an objection is made, and in contractual relations – throughout the term of the contract and thereafter for a period specified in provisions on archiving and limitations period for claims. Anyone has the right to file a complaint with the President of the Personal Data Protection Office. Questions concerning privacy at DZP can be sent to DZP’s Data Protection Inspector, Macieja Maciejewskiego, at: iod@dzp.pl.
New rules on cookies: Domański Zakrzewski Palinka sp.k., as the service provider of the www.dzp.pl website, stores and accesses cookies, i.e. small text information fles sent by a web server and stored on your hard drive, or other data storage medium of a user, for the purposes of: proper functioning of the www.dzp.pl website, confguring the www.dzp.pl website, security and reliability of the www.dzp.pl website, session monitoring, providing advertisements, personalization of the displayed information to the user, or analysis, statistics, research and website trafc auditing.
You can specify the conditions for storage of or access to cookies via your browser settings. Consent to the storage of or access to cookies by Domański Zakrzewski Palinka sp.k. on your device, is acknowledged by the settings of the browser installed on your device. For more information, see our cookie policy.